As part of SGNs commitment to keep you safe and warm, JDT Utilities have been contracted to replace the old cast iron mains with new polyethylene plastic pipes in Pearce Avenue and Elms Avenue as part of an on-going upgrade programme.

We will be utilising temporary signals and road closures in phases. Access will be maintained to all properties, Lilliput Surgery and Parkstone Yacht Club for the duration of our works, either by team liaison onsite or advance warning signage advising diversion route.
 
Please see phase plan below with supporting traffic management drawing, diversion route indicated in blue.
 

Phase 1 will commence from 05/02 and is expected to last for approximately two weeks.

Elms Avenue junct Sandbanks Road will be closed, and a two-way set of lights will be installed on Sandbanks Road.
 

Phase 2 will follow Phase 1 and is expected to last for approximately two weeks.

During this phase, Pearce Avenue from its junction with Elms Avenue to its junction with Parkstone Yacht Club will be closed. 


 

Phase 3 will follow Phase 2 and is expected to last for approximately two weeks.

During this phase, Pearce Avenue junction Sandbanks Road will be closed, and a two-way set of lights will be installed on Sandbanks Road.